Many of your questions may have been answered in one of the following FAQs:
Connecting to Our Electrical System
Welcome to Southern California Edison Grid Interconnections
The information on this page is intended to help our customers understand the requirements and processes for interconnecting projects to SCE’s electric system.
You can navigate through the sections below or you can get started by reviewing our introduction to SCE’s Generator Interconnection Processes.
Announcements
- Find out about unit costs for system upgrades that may be needed for generator interconnection. Example projects are provided to show how these unit costs are applied. For more information, please download SCE’s Unit Cost Guide.
- SCE will be hosting a Pre-Posting Workshop on Thursday, March 7, 2024
- Unit Cost Guide Posting Date – by March 31, 2024
- Post-Update Workshop: April 11, 2024
For questions, please contact AdviceTariffManager@sce.com
- As of December 30, 2022, new Wholesale Distribution Access Tariff (WDAT) Interconnection Requests can be submitted for processing using our Grid Interconnection Processing Tool (GIPT) portal.
- A WDAT User Guide and Training videos are available to help new users.
- As of Monday, July 19, 2021, the new Rule 21 Non-Export Notification Only Process for pre-approved developers became available. Additional information about eligibility, becoming a pre-approved developer, and submitting notifications can be found by navigating to the Rule 21 section of this site. Once in the Rule 21 section, expand the “Rule 21 Non-Export Notification Only Process” menu item.
- As of Wednesday, December 18th, 2019, all-new Rule 21 Non-Export Interconnection Requests are being processed using our new Grid Interconnection Processing Tool (GIPT).
- A User Guide and Training videos are available to help customers with new functionality implemented on August 24, 2020.
- If you have previously submitted requests via the PowerClerk tool(PCI), please continue to access those requests in PCI.
- For Rule 21 Non-Export requests submitted in GIPT you will continue to use GIPT throughout the lifecycle of your project.
- The Interconnection Request fee is also being requested online via ACH payment using an ePay module within GIPT. More information is in the User Guide linked above or contacts InterconnectionQA@sce.com for payment questions.
- For password assistance, please see the following: How to Reset Password.
- After resetting your passcode, please access GIPT using this link: Grid Interconnection Processing Tool (GIPT).
- Installing a Rule 21 Non-Export Energy Storage system sized less than or equal to 10kW?
- Accelerate your project on the path to obtaining Permission to Operate. Providing sufficient documentation up-front can greatly reduce review and processing timelines.
- Please refer to this checklist for more information to see if your project is eligible.
- A presentation from 7/1/2020 is also available for your review.
- Pre-Approved Single Line Diagrams for projects selecting Protection Options 3 or 6 are now available for use. You may download these documents and attach them to your Interconnection Request submittal. If these do not accurately reflect your project, or you are using a different protection option, then you will need to provide your own Single Line Diagram with your Interconnection Request.
- Accelerate your project on the path to obtaining Permission to Operate. Providing sufficient documentation up-front can greatly reduce review and processing timelines.
- WDAT Queue Cluster Window #16 (QC16) is anticipated to open on Tuesday, April 1, 2025 and to close on Wednesday, April 30, 2025. SCE may modify the dates based on CAISO’s Cluster study schedule.
- CAISO Queue Cluster application window pursuant to the CAISO Tariff Appendix DD: The Cluster Application Window will open on April 1 and close on April 15 of each year. If any date set forth is not a Business Day, then the applicable date shall be the next Business Day. If this website information differs from the CAISO Tariff or a CAISO market notice, the CAISO date shall prevail.
- SCE is developing a plan to implement CAISO’s proposed immediate adjustments to Cluster 15 study schedule. Additional information will be provided when it becomes available. Please see Issue-Paper-and-Straw-Proposal-Interconnecton-Process-Enhancements-2023-Mar132023.pdf (caiso.com)
- Presentation on Electrical Independence, Distribution Group Study, and Cluster Study Process dates is available here: February 15, 2024
- On March 1, 2024, SCE implemented the interim methodology for assessing contribution to reliability network upgrades to evaluate projects under Rule 21 Screen Q and WDAT Section 5.5.1 (Interim Methodology). SCE will review the applications on a first come, first served basis and apply the Interim Methodology in order by Queue Position. Due to the very high volume of Rule 21 applications SCE has already received as of March 1, SCE will experience delays in timely processing the applications. Pursuant to Section D.15 of SCE’s Rule 21 tariff, SCE will use Reasonable Efforts in meeting all the timelines provided under Rule 21 particularly as applicable to processing the pertinent Rule 21 Export application submissions. However, SCE estimates it may take up to 20 business days in addition to the timelines set forth in Rule 21 to complete, including, but not limited to, processing applications, deeming the applications complete, engineering reviews, etc. If additional modifications to the established timelines are necessary, SCE will further notify the customer as soon as practicable to provide an estimated completion date and the reason why additional time is needed.
- Please see the Wholesale Distribution Access Tariff section of this website for information regarding tariff updates effective October 30, 2019
- Distribution Group Study (DGS) Application Window #20, Opening Date: Tuesday, October 1, 2024. Closing Date: Thursday, October 31, 2024. For more information, view SCE’s Rule 21 page.
- Catalina Distribution Group Study Application Window, Opening Date: Monday, October 2, 2023. Closing Date: Tuesday, October 31,2023. For more information, view SCE’s Rule 21 page.
- Per Resolution E-5269, SCE’s Request for Rule 21 Site Exclusivity Deviation for Catalina Island’s Clean Energy All-Source Request for Offers was approved on August 10, 2023. Catalina interconnection requests sited at Middle Ranch are exempt from submitted site exclusivity documentation. For more information, view SCE’s Catalina Island All-Source RFO page.
- CAISO’s Distributed Generation Deliverability (DGD) Process. Information and prior years’ DGD allocation results are available on our page regarding Interconnections to the CAISO. Navigate and expand the following header for additional information: CAISO’s Distributed Generation Deliverability Assignment Application Window.
Additional Information
- CAD File Requirements
- Commissioning Procedure
- Distribution Resources Plan External Portal (DRPEP)
- Electrical Service Requirements (ESR)
- Interconnection Handbook
- Interconnection Queue
- Inverter Manufacturer Attestation Form Phase 3 Functions 1 and 8
- Redacted Interconnection Study Reports
- Request Base Case Data
- Rule 21 Unit Cost Guide
Should you have any questions regarding our interconnection processes, please reach out to either the Grid Interconnection and Contract Development (GICD) team or the Net Energy Metering (NEM) team:
Grid Interconnection & Contract Development – Rule 21 Non-Export, Rule 21 Export, Wholesale Distribution Access Tariff (WDAT) and Transmission Owner Tariff (TOT)
Email: interconnectionQA@sce.com
Phone: (909) 274-1106
Mailing Address:
Grid Interconnection & Contract Development
Southern California Edison
2244 Walnut Grove Ave
Rosemead, CA 91770
Email Distribution List:
To subscribe to the GICD mailing list for notices about interconnection events, please email us.
Net Energy Metering – Customers who produce their own electricity through an eligible renewable distributed generation system; a rate option called Net Energy Metering (NEM). The NEM option allows you to receive a credit for the surplus electricity you supply to the electric grid.
Email: nem@sce.com
Phone: (866) 600-6290
Mailing Address:
Southern California Edison
2244 Walnut Grove Ave
Rosemead, CA 91770
Email Distribution List:
To subscribe to the NEM mailing list for notices about interconnection events and updates, please email us.
Rule 21 Ombudsman Information
To address disputes regarding Rule 21 missed timelines, please contact SCE's appointed ombudsman:
Rod Vickers, Project Manager
Email: Rule21.Ombudsman@sce.com
Phone: (714) 895-0211
DISCLAIMER: The guidelines in this section are provided with the intent to help SCE’s customers understand SCE’s Interconnection Procedures. However, in the case of discrepancies with SCE’s rules, such tariffs and regulations will prevail.