Portions of the City of Hanford and northeastern Kings County
Mascot Substation Project
Improving Reliability in Hanford and Northeastern Kings County
The Mascot Substation Project is an important infrastructure upgrade that will enable us to safely and reliably meet the increased demand for electricity in northeastern Kings County.
The Mascot Substation Project includes construction of a new substation, construction of approximately two miles of new, 66-kV sub-transmission lines, and installation of new fiber optic cable and communications equipment to connect the project to our existing telecommunications system. The proposed substation would include equipment to lower the voltage of electricity to 12 kV.
The project is complete.
- 4th quarter, 2009: We filed an application with the CPUC for a Permit to Construct
- 2nd quarter, 2010: Project approved by CPUC
- 3rd quarter, 2012: Construction began
- December, 2012: December 2012: Construction complete
If you have questions or comments about this project, please contact us. Try our toll-free Project Information Line: 1-888-226-9916.