To improve safety and reliability, and comply with California Public Utilities Commission Requirements, SCE is replacing poles along a 3.5 mile stretch of Malibu Canyon Road from Harbor View Drive to Piuma Road.
The project work will reduce the total number of poles along Malibu Canyon Road:
- 82 poles, including existing poles and guy wires, will be removed
- 65 poles will be installed
Construction work is expected to start mid-April 2017 and is scheduled for completion by March 2018 with a break during the summer. Related telecommunications work will take place intermittently throughout the same period.
What to Expect
Construction Schedule:
- Night Work: 9 p.m. to 5 a.m., Sunday night through Friday morning with lane reductions
- Day Work: 9 a.m. to 3 p.m., Monday through Friday work on road shoulder NO lane reductions
- Work will not occur: on weekends, designated “red flag” days when fire danger is extremely high, peak summer months (late-June through September), and the following holidays:
Memorial Day 5/29, Labor Day 9/4, Veteran’s Day Nov 11, Thanksgiving 11/23-24, Christmas 12/24-25, New Year’s 12/31-1/1
Traffic Impacts: Malibu Canyon Road will remain open throughout most of the construction period
-
Night time lane reduction will allow for traffic flow while crews are working
-
Day time work along the shoulder is not expected to impact traffic flow
-
Some full road closures will be required; advanced notification provided when possible
-
Mid-April 2017: Begin pole replacement and telecommunication project constructions
-
Late June 2017: Project pause during the summer
-
October 2017: Project resumes
-
March 2018: Project complete