Downs Substation Project

Open Downs Substation Project Map (PDF)

Powering Ridgecrest for the 21st Century

This project is designed to upgrade the electrical infrastructure serving the greater Ridgecrest area so that we can continue to provide safe, reliable power, especially during extreme weather conditions.

Ridgecrest and adjacent areas of unincorporated Kern and San Bernardino Counties

Project is completed and in-service.

  • December 2010: We filed an application for a Permit to Construct for this project with the CPUC
  • January 2012: CPUC issued Draft Mitigated Negative Declaration (MND)
  • July 2012: CPUC issued Final MND
  • November 2012: CPUC voted to approve the project
  • October 2014: Construction is scheduled to begin
  • April 2016: Project completed and in-service